By KRobinson on Wednesday, 02 April 2025
Category: Current Projects

SiteOne Spring

SiteOne | Storage/Warehouse | Spring, TX

4.02.25 - Building electrical is near completion. Plumbers are working on the fire tank. Overhead doors are installed and the building is trimmed,

3.05.25 - Metal sheeting installation is near completion. Building trim will follow,

2.04.25 - Erectors are hanging the steel,

1.25.25 - The foundation was poured and is curing,

1.23.25 - Preparing for the foundation pour,