O'Neills Inflight Catering

O'Neills Inflight Catering | 10,000 SF Interior Demo and Remodeling | Houston, TX

8.23.24 - Fire inspections are underway. The epoxy flooring is complete,

oneillsaug23

oneillsaug23 2

oneillsaug23 3

oneillsaug23 4

 

8.19.24 - Kitchen equipment installation and electrical trim out work continues,

oneillsaug16

oneillsaug19 2

oneillsaug19 3

oneillsaug19 4

oneillsaug19 5

oneillsaug19

 

8.13.24 - Kitchen work continues. The warehouse is clean and epoxy flooring will follow.

oneillsaug13

oneillsaug13 2

oneillsaug13 7

oneillsaug13 3

oneillsaug13 4

oneillsaug13 5

oneillsaug13 6

oneillsaug13 8

oneillsaug13 9

oneillsaug13 10

 

8.09.24 - Sign installation is underway. The kitchen is nearing completion,

oneillsaug9

oneillsaug9 2

oneillsaug9 3

 

8.07.24 - Kitchen equipment installation continues,

oneillsaug7

 

8.06.24 - Electrical work continues, flooring is nearing completion, the exterior canopy is installed,

oneillsaug6 2

oneillsaug6 3

oneillsaug6 4

oneillsaug6

7.30.24 - Parking curbs are installed, flooring continues, and restroom partition installation is nearing completion,

oneillsjuly30 2

oneillsjuly30 3

oneillsjuly30 4

oneillsjuly30 5

oneillsjuly30

7.26.24 - Flooring continues,

oneillsjuly26

oneillsjuly26 2

 

7.22.24 -

oneillsjuly22 2

oneillsjuly22 3

oneillsjuly22 4

oneillsjuly22 5

oneillsjuly22

7.17.24 - Painting continues,

oneillsjuly17 2

oneillsjuly17 3

oneillsjuly17

7.16.24 -

oneillsjuly16 2

oneillsjuly16 3

oneillsjuly16

7.12.24 - Lights are on,

9D170B89 6B40 4D36 8CAA 1BB621630B0D copy

oneillsjuly12 2

oneillsjuly12

7.10.24 -

oneillsjuly10

oneillsjuly10 2

F01DE201 5380 4C29 8768 EA31EE70012C copy

7.02.24- Inspections are complete and requirements are met, so ceiling tile installation and final clean will follow,

oneills july

oneills july2

 

6.28.24 - Kitchen equipment arrived, restroom partitions are in place, and the final painting is complete,

oneills june28

oneills june28 4

oneills june28 3

oneills june28 2

oneills june28 5

 

6.17.24 - Tile installation is underway,

oneills jun17

6.10.24 - Exterior trim is complete. Ceiling grid installation is complete. Electricians trim out the interior,

oneills june

oneills june2

5.08.24 - Crews are taping, floating, and sanding interior walls,

oneills may

oneills may2

oneills may3

 

4.26.24 - Plumbers are roughing in the plumbing as additional crews begin sheetrocking the interior walls,

oneills april

oneills april2

oneills april3

 

 

3.01.24 - Warehouse steel painting is complete. Crews are currently installing the insulated metal wall panels, 

oneills mar

2.01.24 - Interior buildout demolition continues,

63DE5FC1 A9EB 462C 9C7C 3FA1F1CBB465

oneills feb

B59413EF BE72 46BC 9007 FC783A8CCA02

 

12.04.23 - MEP interior demolition is underway, 

EC92A7F6 F9AA 4037 B919 BF33B94EC160

6C40F787 DA61 4BF4 8DB9 7FEF9B93C469

 This project includes the renovating of an existing 10,000 SF warehouse for commercial kithcen use.

 

 