5.25.23 - Interior crews continue to hang sheetrock. The paving crew is laying out the remainder of paving to be poured,
3.08.23 - Erectors completed their work hanging the steel. The fire sprinkler contract are hanging pipe. The dirt crewmen are cutting grades,
2.08.23 - M&M Erectors are hanging steel for the new facility,
1.17.23 - Crews are pouring the foundation for Humble Sign’s new 35,722 SF facility. Their new facility includes a two-story office and a crane-served warehouse for manufacturing. We built for Humble Sign in 2018 and are excited to be working with them again.
By accepting you will be accessing a service provided by a third-party external to https://www.northwindsconst.com/