Ellington Trade Center

Ellington Trade Center | 110,015 SF Paving and Storm Utilities | Houston, TX

12.22.20 - Crewmen are painting stripes and joint sealing in the NW paving area. Crewmen are also removing existing parking stripes.

12.18.20 - Crews are painting stripes and joint sealing in SE paving area only.

12.07.20 - Crews are dewatering the site, spreading spoils, and loading materials and cleaning equipment. 

11.20.20 - The NE paving pour is underway,

11.14.20 - Storm work continues,

11.11.20 - Crewmen are laying storm,

11.10.20 - 

11.05.20 - Crews began pouring the paving this morning,