6.02.22 - Power was turned on today, allowing the remaining trades to finish their work,
3.03.22 - Interior build out continues. Windows are installed,
2.08.22 - The building is sheeted. Erectors are installing the ridge vents. Framers have completed framing the office walls.
12.22.21 - The foundation was poured today,
7/01/21 - This new 8,600 SF office and warehouse is in permitting. Construction updates will be available on this page, so check back for this location's progress and availablility.