twitter facebook linkedin

smartslider3[2]

Northwinds Construction

View important updates by Northwinds Construction

Commons at Timber Creek

The Commons at Timber Creek | Two 13,020 SF Flex Space Office/Warehouses | Friendswood, TX

Construction is complete on these Industrial Suites. 

C54CBE82 2B9F 4831 844B 58184C1D70D4 copy

1AC79FFA 136C 4CF4 978E 0E538F1E99B6

297CA0BA 7425 418D AFCA 30611961E5A0 copy

EFA20993 182E 4C41 9EAB 4C3B78D3F3E5 copy

7.17.23 - The stucco and stone is complete. Crewmen are installing glass.

IMG 6165 copy

IMG 6166 copy

IMG 6167 copy

IMG 6168 copy

IMG 6169 copy

IMG 6173 copy

IMG 6174 copy

 

4.14.23 -The masons started their work on the stucco. This project is on schedule to be completed in May.

1

 

3.01.22 - Erectors continue to hang steel. The framing crews began framing the front facades. The paving crew will start pouring the paving soon,

15 copy

14 copy

16 copy

 

12.02.22 - Crews began sheeting the buildings,

6

1

12

 

11.17.22 - Crews are erecting the first of the 12,000 SF flex office/warehouse spaces,

Commons4 copy

 

11.06.22 - Crewmen poured the first pad for this project. Spaces are available for sale or lease and range from 3,000 SF to 12,000 SF.

02 copy

01 copy

COMMONS 1 copy

3 copy

Friendswood4 copy

Friendswood3 copy

  1958 Hits
1958 Hits

Big City Manufacturing

Big City Manufacturing | 23,000 SF | Friendswood, TX

1.23.24 - Final clean is complete. Landscaping is installed.

0BD6C680 52A8 4787 8BEF A644FB29AC8E copy

797FAD6A C23E 4A68 B2E7 D90FC9C38964 copy

884C688C 603B 4BDB 89EA 9C98ED21AA07 copy

939DEC6C 288A 4EE4 954C 20C25338B881 copy

C331B695 3575 49DB 86F5 DCABC72FF462 copy

31035EC2 0FEB 4E42 A95D AF30549D04F9 copy

61D807FB CAFD 4AE1 A6BA 6770C95B70D8 copy

 

 

D3AA3738 4014 4D82 95B0 3C1DD4069A3A copy

D81F2F89 F9BA 433B A89C 29C492DC3C6A copy

F490AF31 9C19 4F45 8F5D F92E54F27F3E copy

04208C60 FE41 40AC AC2D 6ABBBB3455FE copy

BF53357C 94CF 4F2D 9D91 8F5C71965574 copy

122E8930 ADA4 48CA 902B 62E5E69ACBCD copy

81F10C2A 4D7A 4063 8C28 994E01EC4E7C copy

 

12.14.23 - Parking area striping is complete,

09AE6B39 8AB1 45C5 ADF8 561E57D210AD copy

9AF3ACD3 CF26 4ACC 9DC4 941AE688EF56 copy

36E4F666 9456 4E39 8271 415C602837BB

3066A27C 1B03 4852 B0A9 919768EA95F1 copy

525669C0 C0A1 4694 9C1A FF83070A442D copy

 

11.29.23 - Glass installation is complete and the ceilings are installed. Power should be turned on next with an expected completion set for next month,

IMG 7242 copy

IMG 7234 copy

IMG 7236 copy

IMG 7237 copy

IMG 7238 copy

IMG 7239 copy

IMG 7240 copy

 

10.25.23 - Interior crews are hanging sheetrock. Concrete crewmen are getting ready to pour the equipment pad,

IMG 7097 copy

IMG 7096 copy

IMG 7095 copy

IMG 7094 copy

IMG 7093 copy

IMG 7092 copy

IMG 7091 copy

IMG 7090 copy

 

7.25.23 - Crews poured the foundation this morning.

IMG 6281 copy

IMG 6272 copy

 

7.20.23 - Crewmen are preparing for next week's pour,

image11 copy

IMG 6222 copy

IMG 6218 copy

 

5.25.23 - Crews are breaking ground on Big City Manufacturing's new facility in Industry Park. This Design/Build project includes a fully air conditioned shop and 3,000 SF of finished office space,

20223 Binford Flipped.jpg copy

IMG 5673.jpg copy

IMG 5676.jpg copy

  1558 Hits
1558 Hits

Katy Industrial Suites

Katy Industrial Suites | 23,660 SF New Custom Office Condos | Katy, TX

12.15.23 - The Katy Commercial Suites are finished and are available for Lease or Sale. Spaces range from 2,088 SF to 12,529 SF,

1000093261

1000093260

 

10.04.23 - The landscaping is scheduled for this week, and the power is to be turned on this week.

IMG 6913 copy

IMG 6916 copy

IMG 6917

IMG 6918 copy

IMG 6919 copy

IMG 6921 copy

IMG 6923 copy

 

4.20.23 - The last of the paving was poured last night. Erectors continue to sheet the buildings,

IMG 2023 04 20 01 40 57 974 copy

IMG 2023 04 20 02 29 28 189 copy

 

3.22.23 - Erectors began hanging steel this week. Half of the paving was poured this morning,

katy industrial suites 1 copy

katy industrial suites 2 copy

 

10.13.22 - Site crewmen broke ground this week on the Katy Industrial Condos. Crewmen have scraped the site and are beginning the pads,

1 copy

2 copy

3 copy

4 copy

 

9.22.22 - Our crews are breaking ground this week on a new Industrial Condominium project in Katy, TX. Two 11,830 SF units are under construction in the Katy-Hockley Business Park Development (4107 and 4109 Katy Hockley Rd). The condominiums will total 23,660 SF and will be ready Q2 2023.

02 copy

01 copy

03 copy

  2511 Hits
2511 Hits

Independence Business Park Phase 3

Independence Business Park Phase 3

7.17.23 -  Site crews began to scrape the site for the third phase of the Independence Business Park for Finial Group. We are building three office / warehouse buildings total (Building 2, Building 6, and Building 7, each being pre-engineered metal buildings with horizontal architectural panels and limestone offices. Bldg 2 will be 46,378 SF with a 2,855 SF office. Building 6 will be a 18,525 SF crane-ready building with a 2,025 SF office, and Building 7 will be a 25,425 SF crane-ready building with a 2,025 SF office.

image3

  686 Hits
686 Hits

Humble Sign Co.

Humble Sign Co. | 35,722 SF | Humble, TX

5.25.23 - Interior crews continue to hang sheetrock. The paving crew is laying out the remainder of paving to be poured,

1 copy

2 copy

3 copy

4 copy

5 copy

6 copy

6 copy

7 copy

8 copy

9 copy

10 copy

11 copy

12 copy

13 copy

 

3.08.23 - Erectors completed their work hanging the steel. The fire sprinkler contract are hanging pipe. The dirt crewmen are cutting grades,

9 copy

8 copy

7 copy

6 copy

5 copy

4 copy

3 copy

2 copy

1 copy

 

2.08.23 - M&M Erectors are hanging steel for the new facility,

humblesign2.08

humblesign2.08 2

 

1.17.23 - Crews are pouring the foundation for Humble Sign’s new 35,722 SF facility. Their new facility includes a two-story office and a crane-served warehouse for manufacturing. We built for Humble Sign in 2018 and are excited to be working with them again.  

10

4

2

  880 Hits
880 Hits

Premier Cryogenics

Premier Cryogenics | New 26,000 SF 20-ton Crane-served Manufacturing Facility | LaPorte, TX

10.13.22 - Erectors are getting close to closing in the South end of the building,

1

2

4

7

 

9.29.22 - Exterior sheeting and interior insulated sheeting are underway,

7

6

5

9.27.22 - Additional paving is poured. M&M Erectors have erected the steel and are installing the wall sheeting,

1

10

12

9.22.22 - Erectors are assembling and lifting the roof sections,

1

9.19.22 - Erectors are shaking out the steel,

1

2

 

  1170 Hits
1170 Hits

Closner Equipment Co.

Closner Equipment Co. | New Office, Warehouse, Repair Bays and Wash Bays | Waller, TX

7.06.22 - The pad and utilities are complete. Crews will begin drilling the piers this week,

Closner 7.06

Closner 7.06 2

Closner 7.06 3

Closner 7.06 4

 

5.16.22 - Sitework continues,

IMG 2022 05 16 15 09 46 728

IMG 2022 05 16 15 07 11 795

IMG 2022 05 16 15 07 24 563

IMG 2022 05 16 15 08 23 044

 

5.15.22 - The project consists of erecting 4 buildings for the Closner Equipment Co.

The buildings are Office, Warehouse, Repair Bays, and a Wash Bay.

Total is about 6.5 acres with new grading, drainage, and paving plan. Lot will be fenced with automatic gates installed.

Detention pond had 858 cubic yards of dirt removed per the civil engineering plans for the offset of drained water. This portion of the project is complete.

 

  1422 Hits
1422 Hits

Independence Business Park

Independence Business Park (Finial Group)| 43,000 SF of New Office/Warehouses | Houston, TX

This project includes two ground-up spec office/warehouses totaling 43,000 SF. Scope of project also includes extending the business park's private drive and utilities.  

3.02.22 - Buildings 4 and 8 are completed,

6812 8 Bldg 8 2

6811 4 3

6812 8 Bldg 8 4

6812 8 Bldg 8 5

 

2.18.22 - Wrapping up work on Buildings 4 and 8,

9

5

2

4

6

11

 

12.29.21 - Stucco and masonry to begin. Landscaping continues for Bldg 4 and began today for Bldg 8. Electricians are digging up the underground conduit to AT&T's conduit at both bldgs,

12.29.21 2

12.29.21 3

12.29.21 4

12.29.21

 

12.23.21 - Ceiling tile installation continues for Buildings 4 & 8, fixtures are installed in both buildings, receptacles and can lights are going in today in both buildings, and crews are hooking up the condenser units for Buildings 4 and 8,

12.22.21 2

12.22.21

 

12.16.21 - Flooring continues,

12.16.21 3

12.16.21 2

12.16.21 4

12.16.21 5

12.16.21

11.05.21 - Waiting on one piece of glass to be installed above the door on Building 8. Plumbers are ready for fixtures as soon as the floors are installed. Electrial work continues for both buildings. 

DJI 0726

DJI 0725

DJI 0717

DJI 0706

 

 

 

10.29.21 - The OH door installation continues for Building 8. Plumbers are also installing the water heater and pipe for Building 8. Electricians continue their work on Buildings 4 and 8,

10.29.21

10.29.21 4

10.29.21 6

10.22.21 - Crews cleaned and backfilled around the seven new concrete drainage flumes. Crews are installing lights and ceiling grid in Buildng 4. Waiitng on AC materials for buildings 4 and 8,

Bldg4 1

Bldg4 2

Bldg4 3

Bldg8

Bldg8 3

Bldg8 5

 

9.07.21 - Northwinds crewmen are working to back fill the south side of Bldg 8, next to the drainage ditch, and dress it up. M&M Erectors continue the wall panel installation on Bldg 4,

Screenshot 2021 09 07 094643

Screenshot 2021 09 07 094549

Screenshot 2021 09 07 094706

Screenshot 2021 09 07 094720

Screenshot 2021 09 07 094738

Screenshot 2021 09 07 094752

Screenshot 2021 09 07 095130

 

8.24.21 - Erectors are lifting Bldg #4's roof,

BLDG4

BLDG4 8.24 2

BLDG4 8.24

 

8.18.21 - Paving was poured for Bldg #8. Erectors are lifting Bldg #4,

Bldg 8 paving

Bldg 8 paving 4

Bldg 8 paving 6

Bldg 4

Bldg 4 3

 

7.24.21 - Foundation was poured this morning for Bldg #4,

DJI 0187

DJI 0207

7.02.21 - Crewmen continue to lay out the sub-sub grade in the paving areas around Bldg. 4 & 8, and are cutting to grade to prepare for select fill,

Screenshot 2021 07 06 094600

Screenshot 2021 07 06 094631

Screenshot 2021 07 06 094651

Screenshot 2021 07 06 094703

 

6.25.21 - We are resuming select fill in the paving areas around pad #8. Cutting the paving sub grade in the west end of pad #4 to be able to get a minimum of 8” of select fill and compacted. Plumbers are backfilling trenches.

 

6.12.21 - Windrowing the select fill on Pad 4 and on Pad 8 to help pull the moisture out. Regrading and compacting to get ready for their test on Monday morning. Working on the ditch on the north side of BLDG. 8. Shaping and grading to drain to the pond inlet.

6.12.21

 

6.11.21 - Site crewmen are laying down the select fill that was stock piled yesterday on Pad 4 and began laying down the select fill that was stock piled yesterday on Pad 4. Crews started the first lift on pad 8, compacting in lifts. The plumbers continue working on the 8” water tie in and continued digging their trench. 

6.11.21

 

6.10.21 - Site crewmen began the select fill in Pad 4 and are compacting in lifts.

6.10.21

6.10.21 1

6.09.21 - Crews are cutting bldg. pad 4 & 8 to sub grade (in preparation for select fill). Running the 324 over pad 8 to compact it. Back filling stabilized. Back filling stabilized sand over the 2 culverts. Began the layout and grading on the north side ditch,

6.09.21 1

6.09.21

 

6.08.21 - Cutting bldg. pad 4 to sub grade and starting on pad 8 to prepare for select fill. Running the Roller and 324 over pad 4 to compact it.

6.08.21

6.08.21 1

 

6.07.21 - Starting the 24” & 15” coverts - excavating to grade, building up hdpe bed with stabilized sand, laying the pipe and back fill to 6” from top of pipe for city inspections. Cutting bldg. pad #4 to sub grade to prepare for select fill. 

6.07.21

 

 

  2237 Hits
2237 Hits

Contact Us

Please let us know your name.
Invalid Input
Invalid Input
Please let us know your email address.
Please let us know your message.