twitter facebook linkedin

More than 30 years
of experience in Texas

previous arrow
next arrow
Slider

Joe's Burgers and Subway Restaurants

Traders Village | 4,000 SF Freestanding Joe's Burgers Restaurant / 4,000 SF Freestanding Subway Restaurant | Houston, TX

7.08.19 - Masons continue to lay the brick as Carpenters install the ceiling treatments for Joe's Burgers. Roofers are installing curbs and electricians are roughing in the lights and switches at Subway.

Joes7.08 2

Joes7.08 3

Joes7.08 4

Joes7.08

Subway,

subway7.08 4

subway7.08 2

subway7.08 3

subway7.08

 

6.27.19 - Spiral ductwork is complete for Joe's Burgers. Vent-a-hood is installed. Masons started the brickwork. 

IMG 8011

IMG 8012

IMG 8014

IMG 8016

IMG 8018

IMG 8019

 

6.25.19 - Window frames are installed and the roof is complete for Joe's Burgers. Electricians are roughing in the electrical, while HVAC contractors hang the spiral ductwork. --The block and water proofing is complete for Subway. Curbs are set and roofers began installing the iso board,

IMG 3124

3

IMG 3129

IMG 3130

1

 

6.07.19 - Crewmen are installing hat channels for Joe's Burgers, and hanging steel for Subway,

IMG 3088

IMG 3089

IMG 3090

IMG 3091

IMG 3092

IMG 3093

6.03.19 - Crews have been addressing the CMU installation, setting embedded plates for the bar joists, and filling walls with concrete. As for Joe's Burgers, crewmen are laying out the roof curbs for the AC and vents, cutting AC access and welding angle supports, framing, and pouring interior curbs. Electrical rough-in is also underway. 

1

2

3

4

 

5.29.19 - Crewmen began CMU installation for the Subway restaurant, which will be completed by the end of this week. We expect steel for this building to be delivered on 5/31, and will begin erecting. 

Steel erecting is complete and inspected for Joe's Burgers. The roof deck is on and framing has begun. Crewmen plan to pour interior curbs and block outs this week, so framing and plywood can be completed.

4

1

2

1

2

3

4

5

6

 

5.06.19 - Erectors began hanging steel and the masons continue to build the CMU walls,

IMG 7756

IMG 7757

IMG 7760

IMG 7761

4.29.19 - . Joes slab was poured last week.  Cmu install is scheduled to start today. As for Subway, crewmen were able to pour beams and prep for the slab pour. Subway's slab pour is scheduled for today and tomorrow.

joes

joes3

joes4

joes5

subway

4.03.19 - Underground is complete. Crews are digging beams and tying steel in preparation for next week's concrete pour,

IMG 7603

IMG 7608

IMG 7609

IMG 7610

 

3.25.19 - Crews are pouring piers today for Joe's Burgers. Plumbers ran the utilities for Subway and are backfilling today,

IMG 7555

IMG 7557

IMG 7558

 

 

3.20.19 - The existing slabs are removed. Plumbers have made the utility connections and the boring for the fire main is complete. Concrete crews began tying steel for the piers.

IMG 7513

IMG 7514

IMG 7515

IMG 7516

3.17.19 - Crewmen ran utilities and poured trench for Joe's Burgers, and finished removing the slab for Subway,

1

2

3

4

5

3.08.19 - Crewmen are saw cutting and breaking out existing slabs, making tie-ins for water, sewer, and gas. 

IMG 2904 thumb

IMG 2905

 

 

 

 

 

 

 

Hoelscher Weatherstrip Manufacturing Co.
Wilson Air

Related Posts

Contact Us

Please let us know your name.
Invalid Input
Invalid Input
Please let us know your email address.
Please let us know your message.