Engineered Air Balance, Co.

Engineered Air Balance, Co. | 6,500 SF Buildout | Spring, TX

7.13.18 - The floors are complete and the customer is moving in,

EAB7.13.18 2

EAB7.13.18 3

EAB7.13.18 4

EAB7.13.18 5

EAB7.13.18

EAB7.13.18 6

6.27.18 - Customer is moving in furniture. Crews are addressing punch out items,

IMG 0804

IMG 0805

IMG 0806

6.15.18 - Bay lights set, handrails set, carpet laid in offices, plumbing fixture set started, amd millwork set,

2

5

13

14

19

20

6.11.18 - Tile is complete. Doors are hung. Ceiling tile installation is underway,

IMG 0514

IMG 0516

IMG 0517

IMG 0519

5.21.18 - Crewmen have completed the mop sink walls. The electrical rough-in and copper pipe is 90% complete. Duct insulation is 95% complete and sheetrock walls are 90% hung,

4

5

8

9

5.07.18 - Crewmen have completed the concrete work. The mezzanine is completed. Demo in ste 100 is completed, mop sink is in, and plumbing and electrical rough-ins are going smooth,

9

16

17

20

22

25

27

29

31

32

4.27.18 - Crewmen finished the concrete work and the mezzanine. Walls in ste 100 are stripped, mop sink is in, and A/C duct work began,

1

2

3

4

5

6

7

8

4.19.18 - Crewmen are forming up steps and housekeeping pads for emergency generators. The structural steel for the mezzanine arrived and the erectors began setting columns,

EAB4.19.18

EAB4.19.18 2

EAB4.19.18 3

 

4.12.18 - The roof deck is insulated. Crewmen have run the domestic copper pipe and began work on the chiller pipe. Overhead electrical piping began, as additional crewmen have poured the truck ramp and equipment pad,

1

2

3

4

5

6

3.23.18 - The plumbing trenches are poured back. Two have been filled in with block,

EAB3.23.18

EAB3.23.18 2

EAB3.23.18 3

EAB3.23.18 5

3.15.18 - Office buildout of an existing concrete tiltwall warehouse,

EAB3.15.18

EAB3.15.18 3

EAB3.15.18 4

EAB3.15.18 2

CEMEX
Humble Sign Co.

Related Posts

Contact Us

  1. Please let us know your name.
  2. Invalid Input
  3. Invalid Input
  4. Please let us know your email address.
  5. Please let us know your message.