10.05.19 - Sheeting is underway,
9.27.19 - Parking lot is poured. Erectors are hanging steel,
9.24.19 - Crews are erecting the building. More paving has been poured,
9.12.19 - The building pad was poured and crews are forming for additional paving,
7.16.19 - Crews are pouring the main drive,
7.11.19 - Crewmen began building the pad and laying out the private road for the business park,
6.28.19 - Sitework is underway for this new 9,300 SF office/warehouse, located off Katy Hockley Road and Clay Road. This new facility is available for Sale or Lease,